None
EN
Walnut Street Bridge Repair Costs To Top $40 Million
[]
Chattanoogan.com Breaking News
Repairs to the Walnut Street Bridge have risen by over $5 million, bringing the total cost to above $40 million.
Southern Road and Bridge of Tarpon Springs, Fla., has asked for a change order for $5,085,828, with a contingency in the amount of $500,000.
The work is for "unforeseen structural steel repairs, light fixture shades, and new CCTV cameras."
Also, Volkert & Associates asked for a change order increase for work on the historic bridge, that has been closed since March.
The Volkert request is for an increase of $435,343.32 for additional structural steel inspection, development of additional repair details, and construction administration services, for a total project cost of $1,331,485.25.