Transport Scotland has once again pushed back the timetable for repairing the M8 Woodside Viaducts in Glasgow by over a year. Transport Scotland said the revised timetable is conditional on there being no further adverse conditions or unforeseen challenges and confirmed the projected cost remains between £126M and £152M. Transport Scotland and Amey say the current works are intended to provide a safe temporary repair while a longer-term solution is developed. Loading…“Despite facing significant challenges, the project has made substantial progress with temporary props installed at 13 pier locations out of 23. In addition, ten of the temporary props have been jacked to assist with supporting the carriageway and taking the load.