Welding issues and worker shortage mean HS2 misses deadline for moving Birmingham bridge
['Peter Plisner']
Rail Magazine
Plans to move a huge viaduct into position during a week-long closure of Birmingham’s Cross City line had to be postponed because of welding issues and a lack of skilled workers, RAIL has learned.
Plans to move a huge viaduct into position during a week-long closure of Birmingham’s Cross City line had to be postponed because of welding issues and a lack of skilled workers, RAIL has learned.
The viaduct is currently being built on piers, which will eventually be used for the Curzon 1 viaduct.
It was scheduled to be moved into place during a seven-day blockade of the Cross City North line with passengers transferring onto bus replacement services.
In a statement HS2 Ltd said: “Progress on the Curzon 2 viaduct has been slower than anticipated due to the complexity of welding and availability of skilled UK workers."
['skilled'
'deadline'
'moving'
'rail'
'closure'
'bridge'
'viaduct'
'hs2'
'curzon'
'city'
'work'
'shortage'
'welding'
'issues'
'mean'
'worker'
'misses'
'line'
'postponed']