While blasting is expected to be completed by the first day of school, work on sidewalks, curbs, and asphalt will continue until the onset of winter weather. That’s according to Near North School Board officials, who released an progress update on the new Parry Sound JK-12 school construction project Aug. 11. Temporary parking and roadways will be in place where possible to start the school year to facilitate traffic flow and parking until substantial completion.” However, construction on some exterior elements of the project, including portions of the parking area, athletic track, and playground, will continue throughout the school year. The full project update can be found at nearnorthschools.ca.