CAG flags poor planning, higher-than-expected costs in Bengaluru Metro
['Kiran Parashar', 'Var Template_Content', 'Sso_Login_Box', 'Xwelcome Backorenter The Email Address Or Mobile Number Associated With Your Account To Sign In. Show Passwordsign Innew To The Indian Express Signupxcreate Your Account It Is Quick', 'Easy.Or Show Passwordnextvalidate Otpregisteralready Have An Account', 'Signin', 'Sso_Social_Box', 'Sign In Withgmailfacebookapple', 'Var Follow_Widget_Data', 'Af_Article_Count']
The Indian Express
The CAG report, tabled in Parliament, covers the Bangalore Metro Rail Corporation Limited (BMRCL) from its inception through March 2021, with financial figures updated to March 2023.
(File Photo)Bengaluru’s Namma Metro suffered from poor planning, lower-than-expected passenger numbers, and rising costs, with a performance audit by the Comptroller and Auditor General (CAG) of India finding that weak land assessment and delays pushed up expenses by over Rs 6,600 crore across Phases 1 and 2.
The CAG report, tabled in Parliament, covers the Bangalore Metro Rail Corporation Limited (BMRCL) from its inception through March 2021, with financial figures updated to March 2023.
CAG reviewed the 117 project contracts worth Rs 27,472.85 crore — 89 per cent of the contract value — along with 75 operation and maintenance contracts worth Rs 348.12 crore.
In its report, CAG highlighted that metro ridership fell well short of projections.