Longmeadow Middle School Building Committee submits 90% of design documents to MSBA
['Peter Tuohy', 'Root', '--M-A-Box-Bp', '--M-A-Box-Bp-L', '.M-A-Box', 'Width', 'Margin-Top', 'Important Margin-Right', 'Important Margin-Bottom', 'Important Margin-Left']
The Reminder
Jones Whitsett Architects provided a rendering of the new Longmeadow Middle School entrance at the Middle School Building Committee meeting on Aug. 5.
Photo credit: LongmeadowTVLONGMEADOW — The Longmeadow Middle School Building Committee is inching closer to the start of construction on the new middle school after unanimously approving to submit 90% of design documents into the Massachusetts School Building Authority for consideration.
Whitsett covered the schematic design estimated budget of $118,909,700 — the targeted cost and the cost approved by the MSBA.
The 90% construction documents after reconciliation estimated the cost at $118,200,224, with around $700,000 under the schematic design estimates.
Fontaine Project Executive Jason Boudreau said 100% of construction documents are coming at the end of September, and the filed sub-bids and non-trade bids at the end of October.