Infra projects report Rs 4.93-L-cr cost overrun
['The Hans India', 'About The Author', 'New Delhi']
Andhra Pradesh Breaking News, Telangana News, Hyderabad News Updates, National News, Breaking News
New Delhi: Infrastructure projects worth above Rs 150 crore each registered a cumulative cost overrun of around Rs 4,92,752 crore, according to a monthly government report for June 2026.
A total of 1,847 ongoing infrastructure projects across 17 Central Ministries/ Departments were monitored and it was found that the total revised cost was Rs 40,54,473 crore compared to their original cost of Rs 35,61,721 crore.
The report, however, did not specify the actual number of projects that faced cost overrun.
The Transport & Logistics sector accounts for the highest number of ongoing projects (1341 projects), with revised estimates of Rs 22.32 lakh crore underscoring priority to connectivity-driven infrastructure growth.
The 1,847 ongoing infrastructure projects include 769 Mega projects (project cost of Rs 1,000 crore & above) with an original cost of Rs 30.51 lakh crore, and 1,078 Major projects (project cost below Rs 1,000 crore and up to Rs 150 crore) amounting to Rs 5.10 lakh crore.