None
IT
Red Sky Energy Nears Yarrow Spud as Three-Well Campaign Progresses
['Nik Hill']
Small Caps
Red Sky Energy (ASX: ROG) is moving closer to the start of a three-well drilling campaign at the Innamincka Dome, with civil works for the Yarrow 4 and Yarrow 5 dual-well pad nearing completion.
Red Sky holds a 20% working interest in the wells, which form the next phase of activity at the producing Yarrow field following the tie-in and commissioning of Yarrow 1 in November 2025.
Yarrow Program Nears DrillingEarthworks at the Yarrow site were delayed by consistent rainfall across the Innamincka region, but the dual-well pad is now approaching completion as the campaign moves towards drilling.
The two-well development program follows Red Sky’s execution of a binding Authority for Expenditure (AFE) with Santos in April, covering Yarrow 4 and Yarrow 5.
The timing has been advised to Red Sky by Santos as operator and remains subject to change depending on weather, access windows and operational scheduling.