Ridge Avenue to close between Simpson, Noyes beginning Aug. 12 as water main construction starts
['Submitted The City Of Evanston']
Evanston RoundTable
Credit: City of EvanstonWater main construction along Ridge Avenue is scheduled to begin Wednesday, Aug. 12, from 7 a.m. to 5 p.m., between Noyes and Simpson streets.
Phased work scheduleConstruction on Ridge Avenue will take place in four phases:Phase 1 (Aug. 12): Installation of a new water main along Ridge Avenue.
Installation of a new water main along Ridge Avenue.
This work will not impact Ridge Avenue traffic, and ramped plates will ensure safe roadway access.
This phase requires a full road closure on Ridge Avenue between Noyes and Simpson streets, from 7 a.m. to 5 p.m.