PEQUOT LAKES — After a quiet few weeks, Pequot Lakes is gearing up for the second phase of this summer's Main and Front streets and utilities improvement project.
Main Street, from Rasmussen Road to just across Patriot Avenue in front of the post office, will be closed to traffic beginning Monday, Aug. 10, with marked detours on streets surrounding Main Street.
The Main Street phase of construction is scheduled to begin Monday, Aug. 17, starting with reclamation of the existing asphalt, the app post said.
Read more Pequot Lakes City Council newsWeekly construction meetings will resume at 9 a.m. Wednesdays at the Cole Memorial Building when the Main Street phase begins.
ADVERTISEMENTThe $2.7 million project should be complete by Nov. 2Pequot Lakes Post appFor up to date notifications, download the "Pequot Lakes Post" app on a cellphone.