None
EN
Venezuela Power Grid Recovery: 600 MW Restored After Devastating Quakes
[]
teleSUR English
Venezuela power grid recovery advances after June’s twin earthquakes, with Corpoelec restoring 450 MW and repairing key transmission infrastructure.
Related: Venezuela: Acting President Names New Electricity Corporation HeadVenezuela Power Grid Recovery Continues After Twin EarthquakesVenezuela power grid recovery efforts continue more than one month after two major earthquakes damaged key generation and transmission facilities across the country.
Its return would add 450 megawatts to the national electricity system out of the 600 megawatts lost after the earthquakes.
The Venezuela power grid recovery program is therefore being carried out on several fronts at the same time.
Geopolitical ContextThe Venezuela power grid recovery has regional implications because electricity infrastructure is directly connected to national development, public health and economic sovereignty.