None
EN
R2.43bn spent on Parliament rebuild with Sona target in sight [PICS]
['Molefe Seeletsa']
The Citizen
The rebuild follows the devastating fire of 2 January 2022, which severely damaged key sections of both the National Assembly and Old Assembly buildings.
Bigger, redesigned National Assembly takes shapeCentral to the project is a significantly expanded National Assembly chamber, designed to accommodate more than double its previous capacity.
The main structural envelope of the National Assembly is now nearing completion at 76%, with the deadline being November 2026.
Old Assembly restoration focuses on long-term stabilityParallel work on the historic Old Assembly building is also progressing, with its substructure 98% complete.
Of this, approximately R1.5 billion is allocated to the Old Assembly and R2.5 billion to the National Assembly.