None
EN
Aecon executes energy storage agreement for 1,200MWh Ontario BESS
['April Bonner']
Energy-Storage.News
Announced 28 July, Aecon executed an energy storage facility agreement with IESO to build, own, and operate the Simcoe battery energy storage system (BESS) project, in which Aecon Concessions is an equity partner.
Image: Pexels/Anurag JamwalInfrastructure and construction company Aecon Group has executed an agreement with Ontario’s Independent Electricity System Operator (IESO) for the 150MW/1,200MWh Simcoe energy storage project in Norfolk County, Ontario.
Announced 28 July, Aecon executed an energy storage facility agreement with IESO to build, own, and operate the Simcoe battery energy storage system (BESS) project, in which Aecon Concessions is an equity partner.
Aecon will also serve as the exclusive engineering, procurement and construction (EPC) provider for the balance of plant works.
The target to begin commercial operations is 2030.