Engineer behind Hilltopper Hall settles for under $1 million
['Anthony Clauson']
WKUHerald.com
Engineering agreed to pay $939,995 in a July 2025 settlement over Hilltopper Hall, according to documents signed by S.E.
Hilltopper Hall could not exceed $1.5 million to demolish.
Engineering’s contract for the construction of Hilltopper Hall, it was responsible for overseeing Sewell and Sewell Architects and Scott, Murphy & Daniel over the course of construction.
The SLF hired Brown + Kubican Structural Engineers, a Kentucky-based firm, to perform a forensic inspection of Hilltopper Hall.
Clay also wrote that during the construction of Hilltopper Hall, S.E.