Analysis of the mid-year budget review against the 2026 budget
[]
MyJoyOnline
Cross-Sector Tracker: Budget Commitment vs. H1 2026 ReportedSector / Line item 2026 Budget commitment H1 2026 reported (MYR) % of annual Flag Big Push Infrastructure Programme GH¢30.0bn (Budget 1144, p.142) GH¢6.5bn paid (MYR 720, p.82); 87 projects commenced, 74 trunk roads/bridges, 10 urban, 3 feeder (MYR 563, p.66); 13 of 87 reached ≥50% completion, incl.
2C, p.93) Provisional H1: GH¢8.142bn and GH¢7.830bn respectively (App.
2C Budget line, p.93) GH¢1.7bn paid (MYR 720, p.81); Appendix 2C provisional actual GH¢1.708bn (p.93) 56.8% Ahead of the 46.0% programmed pace — on track Energy Sector shortfalls (IPPs) GH¢15.2214bn (Budget 1140, p.141; App.
2C, p.93) Provisional H1: GH¢3.481bn (App.
Publish a consolidated reallocation table showing every Budget line reduced to fund the GH¢350m, GH¢226m, GH¢400m and GH¢3.0bn reallocations already disclosed (461-462, 475, 486-488), and any others not yet named.