The Bearspaw South Feeder Main Replacement Project remains on schedule, with approximately two kilometres of new steel feeder main installed across 12 work areas in Bowness, Montgomery and Parkdale, demonstrating significant progress for the over 6km long replacement project. Stage B construction updateStage B feeder main construction began in June and there are now 40 segments of the new steel feeder main installed along 3 blocks on 34 Avenue N.W. until the end of year as crews install steel feeder main pipe, complete utility work and restore affected areas once work is finished. Crews are nearing completion of the microtunneling and installation of the concrete carrier pipe, which will enclose the new steel feeder main. Shaganappi pump station work: is currently estimated to begin in mid-September at the Shaganappi pump station.