Major Delays Threaten Completion of Key Yaoundé Highway Expansion
['Business In Cameroon', 'Economie', 'Banking', 'Energy', 'Comms', 'Media', 'Law', 'Insurance', 'Public Management']
Business in Cameroon RS
The expansion of Yaoundé's northern entry road has fallen significantly behind schedule, raising fresh uncertainty over the completion of one of Cameroon's most important urban transport projects.
As of July 14, 2026, the project was 25.86% complete even though 89.11% of the contractual construction period had already elapsed, according to the Ministry of Public Works.
The ministry believes progress should improve once the remaining land is cleared and the contractor increases its mobilization.
According to the Ministry of Public Works, the discussions involve bridge construction, geogrid-reinforced embankments and recycling sections of the existing roadway.
The ministry did not disclose the value of the proposed adjustments or whether they could increase the project's overall cost.