BMC to restart the concretising of roads from next week
['Cdata', 'Var Template_Content', 'Sso_Login_Box', 'Xwelcome Backorenter The Email Address Or Mobile Number Associated With Your Account To Sign In. Show Passwordsign Innew To The Indian Express Signupxcreate Your Account It Is Quick', 'Easy.Or Show Passwordnextvalidate Otpregisteralready Have An Account', 'Signin', 'Sso_Social_Box', 'Sign In Withgmailfacebookapple', 'Var Follow_Widget_Data', 'Af_Article_Count']
The Indian Express
Ahead of monsoon, the BMC had dug up a mammoth stretch of 525 km of Mumbai’s roads which was 25 per cent of total road length of 2,050 km.
In total, the BMC has earmarked a budget of Rs 17,733 crore to concretise 700 km of roads in Mumbai.
According to civic officials, starting October, the BMC will start concreting as many as 1,350 roads having a total length of 365.44 km.
In the first category they will be taking up 574 roads having a total length of 156.74 km.
Story continues below this adIn the second category, the BMC will take up concretising of 776 new roads having a total road length of 208.7 km.