Mumbai-Ahmedabad bullet train project: NHSRCL completes viaduct launch over Girdhar Nagar ROB in just 12 days
['Anish Mondal', 'Aditi Raja', 'Cdata', 'Var Template_Content', 'Sso_Login_Box', 'Xwelcome Backorenter The Email Address Or Mobile Number Associated With Your Account To Sign In. Show Passwordsign Innew To The Indian Express Signupxcreate Your Account It Is Quick', 'Easy.Or Show Passwordnextvalidate Otpregisteralready Have An Account', 'Signin', 'Sso_Social_Box', 'Sign In Withgmailfacebookapple']
The Indian Express
The work involved launching a 45-metre-long bridge using the Span-by-Span (SBS) method, officials said, adding that the total weight of the span was 1200 metric tonnes.
(Image: NHSRCL)The National High Speed Rail Corporation Limited (NHSRCL) has completed the launching of the viaduct over the Girdhar Nagar Railway Over Bridge (ROB) on the Delhi–Ahmedabad main line of the Western Railway in Ahmedabad.
The work, which is part of the Mumbai–Ahmedabad High Speed Rail Corridor bullet train project, has been completed within 12 days.
The NHSRCL said 19 segments were launched to complete the 45-metre span of the viaduct that runs parallel to the existing railway line.
The span was launched on September 15, over the two-lane Girdhar Nagar ROB, which is one of the busiest in Ahmedabad, connecting Shahibaug, Aswara and Kalupur.