Permission was given for a large scale solar park, with panels mounted across 14 agricultural fields covering some 70 hectares, in January 2023 but construction work only began this summer.
However a construction traffic management plan, intended to mitigate disruption from large heavy trucks having to access the site from narrow country lanes from a B road still hasn’t been put in place or implemented, according to Councillor Alistair Neill.
Gobion Fawr member Cllr Neill asked for the construction traffic plan to be “immediately fully communicated and implemented” with residents at Monmouthshire County Council’s September meeting.
The Conservative told the meeting: “There is still no construction traffic management plan in place, communicated to local residents, and being implemented.
He said: “Can you imagine reversing up a winding road for potentially hundreds of yards to allow these construction vehicles to pass in convoy?