‘Too much reliance’ placed on firm behind faulty drain, derailment inquiry told
['Pa Media', '.Wp-Block-Co-Authors-Plus-Coauthors.Is-Layout-Flow', 'Class', 'Wp-Block-Co-Authors-Plus', 'Display Inline', '.Wp-Block-Co-Authors-Plus-Avatar', 'Where Img', 'Height Auto Max-Width', 'Vertical-Align Bottom .Wp-Block-Co-Authors-Plus-Coauthors.Is-Layout-Flow .Wp-Block-Co-Authors-Plus-Avatar', 'Vertical-Align Middle .Wp-Block-Co-Authors-Plus-Avatar Is .Alignleft .Alignright']
STV News
Network Rail placed “too much reliance” on the contractor that built a faulty drainage system that led a train to derail in 2020, an inquiry has heard.
“When the project is in process, Network Rail does not oversee the project on a daily basis,” he said.
Both witnesses said that since the derailment, there had been a “massive focus” within Network Rail on ensuring this documentation is now provided as part of every project.
A criminal prosecution saw Network Rail fined £6.7 million in 2023 after it admitted health and safety failings over the crash.
A Network Rail spokesperson said on Monday the Government-owned company is “committed to supporting the work of the inquiry and continuing to deliver on the recommendations made by RAIB”.