PETALING JAYA : The Shah Alam light rail transit line project (LRT3) has recorded positive progress, with five out of 22 train sets completing a key testing milestone, Prasarana Malaysia Bhd said today. “These five train sets are from Group 1, having passed the FFR with stable and consistent operational performance,” it said in a statement. Once testing for train sets in Groups 1 and 2 is completed, contractor Setia Utama LRT3 Sdn Bhd will be given seven days to update and optimise the software and operational systems. FFR testing will then continue with Group 3, comprising the remaining eight train sets, with completion targeted by Feb 28. Prasarana CEO Amir Hamdan said in December that the LRT3 line would be launched after completion of the testing and commissioning phase.