Y-12 demolition complete
[]
News Archives - Nuclear Engineering International
Teams dismantle the final walls of the Alpha-2 building at the Y-12 National Security Complex (Credit: US DOE)The final wall of a 325,000-square-foot former uranium enrichment facility has been taken down, marking the completion of the Oak Ridge Office of Environmental Management’s (OREM) largest demolition project yet at Y-12 National Security Complex.
Crews will begin tearing down the 9401-1Steam Plant in the summer, and OREM and UCOR will also complete deactivation on the next former uranium enrichment facility slated for near term demolition: the 210,000-square-foot Beta-1 facility.
The Department of Energy (DOE) Y-12 National Security Complex managed by Consolidated Nuclear Security, is a central pillar of the US Nuclear Security Enterprise.
While several subprojects (site readiness, substation, PSF) are complete, the overall project has faced significant cost and schedule increases.
It was originally slated for completion by 2025–2026, but the National Nuclear Security Administration (NNSA) now expects the facility to reach full operations by 2034.